The building project has been broken down into 4 main phases:
| Phase | Cost | Status |
| 1. Purchase and rezoning of land | R 1,208,687 | Complete |
| 2. Earthworks and Civils | R 2,716,000 | Complete |
| 3. Cluster of first 5 homes plus key ancillary buildings |
R 3,345,430 | Construction of the first 3 homes completed in July 2011. Construction of key ancillary buildings to commence shortly with completion of final 2 homes in Cluster 1
|
| 4. Building of remaining 4 clusters of 5 homes |
R 9,441,505 | |
|
TOTAL ESTIMATED CAPTIAL EXPENDITURE |
R 16,711,622 |
The land for the development of the Village was purchased in 2009, the project management team then had to undergo the process of getting the 30 acres of agricultural land rezoned. This process was completed on the 31 August 2010 with earthworks commencing 1 September 2010. The first phase of building started in January 2011 and involved the construction of 3 homes in the first cluster. THese homes were completed in July 2011.
The next phase of building will include the construction of key ancillary buildings, including the Community Hall and Preschool. This will commence in the latter part of 2011. View our building blog to see the full story of the progress on site.
A full tender process was followed, and the contract for the earthworks was awarded to Inhlanhla Civils, and the construction contract was awarded to Brayshay Construction.